DK Rating: Design C- / Construction B / Finish C+
|
3 October 2001 |
| 14 October 2001 |
| 25 October 2001 |
| 19 November 2001 |
| 28 November 2001 |
| Talking with supervisor.. he estimated completion by End November. My concern about the design I believe will stay true...steep angles with abrupt transitions into the flat bottom. Also the architects are going over board.. making the concrete way to hard to work with (fiber-crete plus hardening additives) and not allowing the contractor to be able to trowel the concrete to a super smooth finish...expect this one to be smooth, with some decent lines but some obstacles not as functional as could have been and the surface will probably be a little lumpy, imperfect in some spots, white and chalky. |